| |
Appeals
Court of Massachusetts
MANUEL
F. SPENCER & SON, INC.
v.
COMMONWEALTH (and two companion cases).FN1
Decided
June 30, 1983.
| |
FN1.
Ashland Oil, Inc. v. Manuel F. Spencer & Son,
Inc. & BMC Durfee Trust Co.; Ashland Oil,
Inc. v. Commonwealth. |
Before ARMSTRONG, KAPLAN and KASS, JJ.
KAPLAN,
Justice.
Our
main task on these appeals is to make our way through
their procedural entanglements. At the end of the
trial lie a few narrow substantive questions.
We
begin with a bare sketch of the facts.FN2 The Commonwealth
contracted with Ashland Oil, Inc. (Ashland), for the
reconstruction of an eleven mile stretch of Route
3 from Duxbury to Plymouth. Ashland, as general contractor,
entered into two contracts, dated March 15 and June
30, 1978, with Manuel F. Spencer & Son, Inc. (Spencer),
as subcontractor, by which the latter was to do certain
drainage work. The venture required cooperation between
the two companies. Spencer was to install subsurface
drainage structures, then Ashland was to pave them
over with a layer of gravel topped by a layer of bituminous
concrete. The next step was for Spencer to dig through
these layers in order to do further work connected
with the drainage structures and to lay manholes,
grates, and other openings at the road level. The
joint effort apparently broke down in the summer of
1978. Ashland began to omit the gravel layer in favor
of the concrete, which increased Spencer's burden
in reaching the drainage structures and carrying out
the other jobs of the second stage of its work. Further,
Ashland, in order to expedite its own work, required
Spencer on various occasions at considerable expense
to discontinue operations and relocate. Around March,
1979, Ashland commenced withholding payments due to
Spencer on the ground, apparently, that Spencer was
not fulfilling its obligations, and this in turn caused
Spencer to fail in its duty under the subcontracts
to make payments of "health and welfare benefits
contributions" to its employees' union. On April
9, 1979, Ashland cancelled the **1107 subcontracts-unjustifiably,
as Spencer claimed.
| |
FN2.
This short account is drawn from the testimony
and findings in the joint trial mentioned below.
Here began some procedural sorties. Spencer,
under the statute providing in given situations
for direct payment by awarding authorities to
subcontractors (G.L. c. 30, § 39F), made
demand on the Commonwealth by letter of August
28, 1979 (with copy to Ashland) for $97,343.03
as the balance owing to it in connection with
the subcontracts. The demand was considered
by the responsible Commonwealth department to
be insufficient under the statute for lack of
a breakdown of items (see § 39F[1][d] ).
Ashland responded by a letter of September 6,
1979, to the Commonwealth (copy to Spencer)
which was considered to be insufficient for
the same reason (it was also unsworn).
FN3
The Commonwealth did not make direct payment.FN4
FN3. A further Ashland letter of September 18,
1979, did provide some breakdown, but it was
unsworn.
FN4.
Nor, evidently, did the Commonwealth act under
§ 39F(1)(f) to make a bank deposit of the
amount disputed by the general contractor.
|
To enforce its alleged direct-payment claim, Spencer
brought suit against the Commonwealth in Superior
Court on October 3, 1979 (see § 39F [4] ). When
the Commonwealth answered, raising among other things
the inadequacy of Spencer's demand, Spencer moved
for summary judgment. At this point, Ashland, a nonparty,
moved in the action to be added as a party under Mass.R.Civ.P.
19(a), 365 Mass. 765 (1974) ("Persons to be Joined
if Feasible"), asserting that it owed nothing
to Spencer and that it might suffer prejudice if the
action were carried on in its absence. The judge denied
Ashland's motion, pointing to the statement in §
39F(4), as inserted by St.1972, c. 774, § 2:
"A subcontractor shall enforce a claim for direct
payment ... by a petition in equity in the superior
court against the awarding authority and the general
contractor shall not be a necessary party" (emphasis
supplied).FN5 He also denied without prejudice a supplementary
oral motion by Ashland to intervene in the action
under Mass.R.Civ.P. 24(a), 365 Mass. 769 (1974)-this
on the ground that Ashland had not tendered the pleading
required for intervention by Mass.R.Civ.P. 24(c),
365 Mass. 770 (1974). The judge likewise denied, without
prejudice, Spencer's motion for summary judgment,
mentioning the insufficiency of Spencer's demand letter.
| |
FN5.
We shall deal later with the quoted language,
but it may be said here that Ashland's motion
was unusual: usually it is a party who moves under
rule 19(a) to dismiss the action unless his opponent
takes steps to join some designated third person
as a party. Ashland's better motion would have
been to inject itself into the action as an intervenor,
and it did later so move as indicated in our text
immediately below. |
Instead
of perfecting its motion to intervene in Spencer's
action, Ashland on June 11, 1980, commenced an action
in Superior Court against Spencer, praying a declaration
of the rights and duties of the parties. A second
judge, viewing the actions of Spencer vs. Commonwealth
and Ashland vs. Spencer FN6 as companions, led the
parties to prepare a single "statement of the
issues" in both actions in lieu of an elaboration
of the pleadings.
| |
FN6.
BMC Durfee Trust Co. was an added defendant (see
note 1) but this may be disregarded. A separate
action by Spencer against Aetna Casualty &
Surety Co., surety for Ashland, plays no part
in the present appeals. |
The
two actions were tried to a third judge sitting without
a jury. Although the actions were in fact tried together
rather than in sequence, no order of consolidation
was entered. The Commonwealth was early excused from
participating since it expressed no preference as
between Spencer and Ashland. Evidence was taken for
eight days. The judge made findings, rulings of law,
and order for judgment in Ashland vs. Spencer to the
effect that Ashland was not justified in terminating
Spencer and was, instead, itself guilty of breaches
of its duties toward Spencer in respect of both the
physical performance and the withholding of payments;
that Ashland was liable to Spencer in the amount of
$78,252.13; and that Ashland had no claim against
Spencer. Correspondingly, in Spencer vs. Commonwealth
the judge held for Spencer against the Commonwealth
in the same amount. Ashland's motion for a new trial
in Ashland vs. Spencer was denied. It moved again
(after judgment) to intervene in Spencer vs. Commonwealth
and that motion was also denied.
Thereafter,
on May 21, 1981, Ashland sued the Commonwealth in
Superior Court alleging that it had substantially
completed its contract; that the Commonwealth had
accepted the work; and that a balance of $78,252.13
was due it, for which it prayed judgment. A motion
by the Commonwealth to dismiss, reciting res judicata
as a ground, was denied, but a fourth judge finally
allowed summary judgment in the Commonwealth's favor
on that ground (adding that Ashland had made an inadequate
response to Spencer's demand).
The
following matters are before us. In Spencer vs. Commonwealth,
the Commonwealth has waived appeal, but we have a
purported appeal by Ashland from the judgment for
Spencer, with Ashland also claiming error in the denial
of its joinder motion under rule 19(a) and its motions
to intervene under rule 24(a).FN7 In Ashland vs. Spencer,
Ashland appeals from the judgment for Spencer and
the denial of its new trial motion.FN8 In Ashland
vs. Commonwealth, Ashland appeals from the judgment.
| |
FN7.
We make the questionable assumption that Ashland
preserved on this record rights of appeal from
the denials of the joinder and intervention
motions. Cf. Mayflower Dev. Corp. v. Dennis,
11 Mass.App. 630, --- - ---, Mass.App.Ct.Adv.Sh.
(1981) 688, 691-693, 418 N.E.2d 349. We deal
with the intervention question although Ashland
does not argue it specifically; it does argue
the denial of joinder. Insofar as Ashland may
possibly be entitled to attack the substance
of the judgment for Spencer against the Commonwealth,
that is treated in effect when we consider the
correctness of the judgment in Ashland vs. Spencer.
Ashland claimed an appeal from the denial of
its application for a stay of that judgment,
but the appeal may be disregarded for present
purposes.
FN8.
Ashland does not argue the new trial point and
it may be disregarded. Spencer cross-appealed,
presumably to increase its recovery, but it
has not briefed its appeal and has thus abandoned
it.
|
Ashland
offers a farrago of legal arguments but they do not
come to much. It reasserts that Spencer's demand was
faulty, while apparently minimizing the troubles with
its own response. The Commonwealth, having once taken
the position that Spencer's demand was inadequate,
now, in its brief to this court argues the contrary
and criticizes Ashland's response.FN9 We are not to
be taken as derogating from the importance of proper
detail in demand and response under § 39F; indeed,
the smooth conduct of the direct payment procedure
may depend on it. In the present circumstances, however,
after a lengthy adversarial trial on the merits in
which all aspects of the facts have been explored,
there can no longer be any reasonable protest about
lack of notice of claim or defense. There is no occasion
now to read the initiating papers with eagle's eyes
as if the subject-matter jurisdiction of the court
depended on their technical sufficiency.FN10
| |
FN9.
The Commonwealth's change of heart is understandable.
Apparently it has paid Spencer the amount of
the judgment in Spencer vs. Commonwealth.
FN10.
Ashland is also hypertechnical in arguing that
the trial judge's casual reference to the Commonwealth's
situation as that of a "stakeholder"
shows that the authority of § 39F for obtaining
a judgment against the Commonwealth was exceeded
in the Spencer vs. Commonwealth action. Also
captious are criticisms about the reception
of evidence at trial that may have gone somewhat
beyond the bounds of the "statement of
the issues" strictly considered.
|
Ashland
argues that it should have been admitted as a party
to Spencer vs. Commonwealth. It had a fair case for
intervention under rule 24(a). See Selectmen of Stockbridge
v. Monument Inn, Inc., 8 Mass.App. 158, 162, 39 N.E.2d
1265 (1979), and cases cited. See also Haverhill v.
DiBurro, 337 Mass. 230, 235-236, 148 N.E.2d 642 (1958);
Smith & Zobel, Rules Practice § 24, Reporters'
Notes, at 157 (1975) (an applicant is entitled to
intervene in an action when his position is comparable
to that described in rule 19[a][2][i] ). The language
quoted from § 39F(4), that the general contractor
is not a "necessary" party, may carry the
meaning that the subcontractor is not required to
join the general contractor as a party as a condition
of maintaining an action against the awarding authority
even if the general is amenable to service of process:
if the general, on notice of the subcontractor's demand,
is content to remain on the sidelines, the action
may proceed.FN11 But that is not to deny the possible
propriety in given circumstances of an intervention
by the general contractor, for the subcontractor's
action deals with an amount due to the general under
its contract with the awarding authority if the subcontractor
does not have a superior claim for direct payment
under the statute.FN12 If Ashland had a just case
for intervention, it nevertheless chose not to perfect
its original motion to that end during the pendency
of the action; and there was surely no error in denying
the motion made after judgment. See Selectmen of Stockbridge,
supra. However, all that we have said about joinder
and intervention is vain, since the overriding fact
is that for practical purposes Ashland was deprived
of nothing by its exclusion from Spencer vs. Commonwealth:
it made every material contention on its own behalf
in the action of Ashland vs. Spencer which was tried
in tandem, although not officially consolidated.
| |
FN11.
The statute, dating from 1972, uses the term
"necessary" which is redolent of codes
of procedure antedating the Federal Rules of
Civil Procedure and was also used in the initial
version of the Rules. The term does not appear
in the present Federal Rules or in our analogous
rules. "Necessary" party usually meant
a person whose joinder was required if service
could be effected; an "indispensable"
party had to be joined in any event on pain
of dismissal of the action. See Clark, Handbook
on the Law of Code Pleading 360-362, 380-382
(2d ed. 1947); James & Hazard, Civil Procedure
§ 9.14, at 427-428 (2d ed. 1977). Whether
the draftsmen of the 1972 statute were conscious
of these usages is not clear.
FN12.
Similarly we can imagine the Commonwealth seeking
in some circumstances to join a general contractor
under rule 19(a). See note 5.
|
The
latter action comprised the merits. Ashland attacks
the judgment, first, on the ground that the judge
received, over objections, exhibits consisting of
abstracts from ledgers kept by the Commonwealth's
assistant resident engineer to measure work performed
on the project. The abstracts were made when Spencer
was obliged to leave the job, but before any civil
action was begun. There is no claim that the abstracts
did not reflect truthfully the underlying entries.
We think the papers offered were "made in good
faith in the regular course of business and before
the beginning of the civil ... proceeding" within
the meaning of G.L. c. 233, § 78, as appearing
in St.1954, c. 442. See Bates Block Associates v.
Milady's Shop, Inc., 3 Mass.App. 776, 333 N.E.2d 214
(1975). See also Greenberg v. Weisman, 345 Mass. 700,
703, 189 N.E.2d 531 (1963); Dyecraftsmen, Inc. v.
Feinberg, 359 Mass. 485, 487, 269 N.E.2d 693 (1971).
Second,
Ashland argues that some parts of Spencer's claim
allowed by the judge did not fit the language of the
statute which gives a right of direct payment for
"the balance due under the subcontract including
any amount due for extra labor and materials furnished
to the general contractor" (§ 39F[1][e],
as inserted by St.1972, c. 774, § 2). We do not
attempt a definition of "extra labor and materials"
that would suit all contingencies of the statute.
It is enough to say that work done by a subcontractor
to achieve the goals of the subcontract that is made
necessary by the general's negligence, carelessness,
or wrongful act, qualifies as extra work. See 17A
C.J.S., Contracts § 370(3), at 396-398 (1963),
and cases cited. FN13 Spencer's exertions due to Ashland's
failure to lay down gravel were clearly extra work.
See Baccari v. B. Perini & Son, 293 Mass. 297,
302-303, 199 N.E. 912 (1936).FN14 We think the same
holds for Spencer's additional work and consequent
costs occasioned by the multiple disruptions and relocations
for which Ashland was responsible. See Johnson v.
Fenestra, Inc., 305 F.2d 179, 181 (3rd Cir.1962).
See also J.I. Hass Co. v. D.M.W. Contr. Co., 143 N.Y.S.2d
917, 920 (Sup.Ct.1955), aff'd, 1 A.D.2d 770, 149 N.Y.S.2d
213 (1956).FN15
| |
FN13.
Ashland makes a point of the fact that Spencer
sometimes referred to such costs as "hardship"
costs, but that characterization was entirely
consistent with its claim for extra work.
FN14. The judge thought Ashland overused concrete
in order to increase its profit margin.
FN15. There is no question here of the Commonwealth's
bearing the costs for any of the extra work: the
Commonwealth paid Spencer out of moneys it reserved
to cover the costs of its contract with Ashland. |
Third,
Ashland points out that no "accounting,"
as such, appears in the findings, whereas the "statement
of the issues" characterizes two of the "issues"
as dealing with the "state of accounts"
between Spencer and Ashland. The need for any elaborate
mathematics looking like an "accounting"
was obviated once it was decided that Spencer was
not liable for any of Ashland's costs in doing the
subcontract work remaining to be done after Spencer
was wrongfully dismissed from the job. Ashland does
not manage to show that the figures found by the judge
to make up the amount owing to Spencer are "clearly
erroneous" in the light of the evidence adduced.
See Mass.R.Civ.P. 52(a), 365 Mass. 816 (1974).
Ashland
vs. Commonwealth was correctly decided on principles
of res judicata. Even if, despite the practical fusion
of the two actions tried to the judge, Ashland is
conceived not to have confronted the Commonwealth
therein as an adversary, we still have a situation
where Ashland, as plaintiff, has failed on the critical
issues as against Spencer. According to modern ideas
of "issue preclusion," Ashland's failure
carries over and defeats it in its action against
the Commonwealth with respect to a fund otherwise
owing by the Commonwealth to Ashland. See Restatement
(Second) of Judgments § 29 (1982), and the discussions
of this principle of preclusion in Albernaz v. Fall
River, 346 Mass. 336, 339-340, 191 N.E.2d 771 (1963);
Home Owners Fed. Sav. & Loan Assn. v. Northwestern
Fire & Marine Ins. Co., 354 Mass. 448, 451-456,
238 N.E.2d 55 (1968), and dissents, id. at 456-461,
238 N.E.2d 55. (See also Rudow v. Fogel, 376 Mass.
587, 592-593, 382 N.E.2d 1046 [1978], commenting on
the Home Owners case.)
Judgments
affirmed.
back to top
|