| |
Appeals
Court of Massachusetts
TLT
CONSTRUCTION CORP.
v.
A. ANTHONY TAPPE AND ASSOCIATES, INC., & another.FN1
No.
97-P-469.
Decided
Sept. 30, 1999.
FN1. Jeffrey M. Hoover.
Present:
WARNER, C.J., PERRETTA, & LENK, JJ.
LENK,
J.
This
litigation arises from construction-related disputes
between an architect and a general contractor, both
of whom had been retained by a municipal owner in
connection with a library renovation project. After
securing an award in arbitration from the owner for
claims based primarily on the architect's actions,
the general contractor sued the architect directly
for various torts including negligent misrepresentation,
interference with contractual relations, and defamation,
as well as for unfair and deceptive practices pursuant
to G.L. c. 93A. The general contractor's claims arise
from the architect's conduct before and during construction,
and from a post-construction evaluation of the general
contractor made by the architect to the State certifying
authority. The trial court judge granted the architect's
motion for summary judgment on all claims; those arising
out of the postconstruction evaluation were dismissed
because the general contractor had insufficient proof
of an essential element of its claims, viz., damages,
and the remaining claims were dismissed on the basis
of res judicata.
On
appeal, the general contractor contends (a) that the
general contractor's prior arbitration proceeding
against the project owner does not operate as a claim
or issue preclusion bar to its direct tort claims
against the architect arising from the architect's
project performance; (b) that the trial judge erred
in granting summary judgment on the evaluation-based
claims because there is a genuine issue of material
fact as to whether the general contractor suffered
damages; and (c) that it was error to grant summary
judgment on the general contractor's claims for G.L.
c. 93A violations because res judicata is inapplicable
and there are genuine issues of material fact as to
whether the general contractor suffered damages.
We
affirm in part and reverse in part.
Factual
background. The materials before the judge, viewed
in the light most favorable to the nonmoving party,
disclose these facts. See, e.g., Yakubowicz v. Paramount
Pictures Corp., 404 Mass. 624, 626, 536 N.E.2d 1067
(1989). In order to renovate and construct additions
to the Beverly Public Library (project), the city
of Beverly (owner) entered into a contract (architect
contract) with the project architect, A. Anthony Tappe
and Associates (architect), and a separate contract
(construction contract) with the general contractor,
TLT Construction Corporation (contractor). The project
did not proceed smoothly. The architect's failure
to make decisions and review submittals in a timely
manner caused the construction schedule to suffer
from various delays and disruptions. Discrepancies
in, and subsequent modifications to, the architectural
plans caused the contractor to use more building materials
and to perform more repair work than anticipated.
Pursuant
to the construction contract, the contractor brought
an arbitration proceeding against the owner (prior
arbitration) in which it sought to recover damages
for extra costs incurred on the project. Among other
things, the contractor sought damages for additional
building materials and labor necessitated by discrepancies
in and modifications to the architectural plans (building-related
claims), and for employing a superintendent for longer
than anticipated (delay claims). Although the architect
testified and submitted documents at the arbitration
hearing, it was not, and contractually could not have
been, joined as a named party in the prior arbitration.
Because the construction contract included a "no
damages for delay" clause as required by G.L.
c. 30, § 39O, the arbitrator determined that
the contractor was not entitled to delay damages,
and, after hearing the evidence, allowed the owner's
motion to strike the contractor's delay claims. The
arbitrator essentially found the contractor and the
owner each fifty percent responsible for building-related
damages, and awarded the contractor half of the costs
incurred.
Following
completion of project construction, the architect
evaluated the contractor's performance on the project
and submitted a project evaluation form to the Massachusetts
Division of Capital Planning and Operations (DCPO)
pursuant to the public bidding statute, G.L. c. 149,
§ 44D.FN2 This evaluation, according to the contractor,
contains false and defamatory statements and misrepresentations.
It was not addressed in the prior arbitration.
| |
FN2.
General contractors wishing to bid on contracts
subject to the public bidding statute, G.L. c.
149, §§ 44A-H, must meet eligibility
requirements as set forth by the DCPO. At the
conclusion of such projects, the person responsible
for oversight of the building construction contract
must complete a project evaluation form. DCPO
uses this form to determine the contractor's eligibility
for bidding on future public projects. |
In
its subsequent Superior Court action brought directly
against the architect, the contractor seeks to recover
damages for negligent misrepresentation, interference
with contractual relations with the owner, interference
with advantageous business relations with DCPO, violation
of G.L. c. 93A, and various torts including intentional
and negligent misrepresentations, fraud, deceit, and
defamation. For ease of discussion, we break these
somewhat amorphously pleaded claims into several broad
categories: (1) the contractor's tort claims arising
out of the architect's performance on the project,
including both building-related claims and delay claims
(performance-based claims); (2) the contractor's tort
claims arising out of the architect's evaluation of
the contractor's project performance; and (3) the
contractor's claims under G.L. c. 93A arising out
of the architect's project performance and evaluation
of the contractor.
Discussion.
1. The contractor's tort claims arising out of the
architect's project performance. The architect asserted
its entitlement to summary judgment on these claims
based upon the defense of res judicata. It argued,
and the judge agreed, that the prior arbitration between
the contractor and the owner precludes the contractor's
building-related and delay claims brought directly
against the architect in the current action.
"The
term 'res judicata' includes both claim preclusion
and issue preclusion." Sarvis v. Boston Safe
Deposit & Trust Co., 47 Mass.App.Ct. 86, 98, 711
N.E.2d 911 (1999). "The doctrine of claim preclusion
makes a valid, final judgment conclusive on the parties
and their privies, and bars further litigation of
all matters that were or should have been adjudicated
in the action." Heacock v. Heacock, 402 Mass.
21, 23, 520 N.E.2d 151 (1988). For claim preclusion
to bar the contractor's building-related and delay
claims against the architect, "three elements
are required: (1) the identity or privity of the parties
to the present and prior actions; (2) identity of
the cause of action; and (3) prior final judgment
on the merits." Gloucester Marine Rys. Corp.
v. Charles Parisi, Inc., 36 Mass.App.Ct. 386, 390,
631 N.E.2d 1021 (1994).
"The
doctrine of issue preclusion 'prevents relitigation
of an issue determined in an earlier action where
the same issue arises in a later action, based on
a different claim, between the same parties or their
privies.' [ Heacock v. Heacock, 402 Mass. at 23 n.
2, 520 N.E.2d 151.] It requires proof that '(1) there
was a final judgment on the merits in the prior adjudication;
(2) the party against whom estoppel is asserted was
a party (or in privity with a party) to the prior
adjudication; and (3) the issue in the prior adjudication
is identical to the issue in the current adjudication.
Additionally, the issue decided in the prior adjudication
must have been essential to the earlier judgment.'
Commissioner of the Dept. of Employment & Training
v. Dugan, 428 Mass. 138, 142, 697 N.E.2d 533 (1998)
(citation omitted). Issue preclusion can be used only
to prevent relitigation of issues actually litigated
in the prior action. Fidelity Mgmt. & Research
Co. v. Ostrander, 40 Mass.App.Ct. 195, 199, 662 N.E.2d
699 (1996), and thus we look to the record to see
what was actually litigated. See Gleason v. Hardware
Mut. Cas. Co., 324 Mass. 695, 699, 88 N.E.2d 632 (1949)."
Sarvis, supra at 98-99, 711 N.E.2d 911. As the party
moving for summary judgment on the basis of claim
and issue preclusion, the architect bears the burden
of establishing each of these factors. Sarvis, supra
at 99, 711 N.E.2d 911. Pederson v. Time, Inc., 404
Mass. 14, 16-17, 532 N.E.2d 1211 (1989).
a.
Identity or privity of the parties. Claim preclusion
has as a prerequisite that there be an identity or
privity of the parties to the present and prior actions,
while issue preclusion requires that the party against
whom issue preclusion is asserted in the present action
was a party or in privity with a party to the prior
adjudication. The architect and the owner are not
identical, but the architect claims privity with the
owner pursuant to the architect contract between the
owner and the architect as well as the construction
contract between the contractor and the owner. On
this basis, the architect contends that it can use
the prior arbitration award to preclude the contractor's
building-related and delay claims in the current action.
"[O]ne
not a party to the first action may use a judgment
in that action defensively against a party who was
a plaintiff in the first action on the issues which
the judgment decided." Home Owners Fed. Sav.
& Loan Assn. v. Northwestern Fire & Marine
Ins. Co., 354 Mass. 448, 455, 238 N.E.2d 55 (1968).
Bailey v. Metropolitan Property & Liab. Ins. Co.,
24 Mass.App.Ct. 34, 36, 505 N.E.2d 908 (1987). "A
nonparty to a prior adjudication can be bound by it
'only where [the nonparty's] interest was represented
by a party to the prior litigation.' " Massachusetts
Property Ins. Underwriting Assn. v. Norrington, 395
Mass. 751, 754, 481 N.E.2d 1364 (1985), quoting from
Mongeau v. Boutelle, 10 Mass.App.Ct. 246, 249-250,
407 N.E.2d 352 (1980). See Morganelli v. Bldg. Inspector
of Canton, 7 Mass.App.Ct. 475, 481, 388 N.E.2d 708
(1979); Roche v. Roche, 22 Mass.App.Ct. 306, 309,
493 N.E.2d 523 (1986). See also Note, Developments
in the Law-Res Judicata, 65 Harv. L.Rev. 818, 855-865
(1952); Vestal, Res Judicata/Preclusion 120-124 (1969);
Vestal, Res Judicata/ Preclusion: Expansion, 47 S.
Cal. L.Rev. 357, 360-362, 373 (1974); Cortell, The
Expanding Scope of the Res Judicata Bar, 54 Tex. L.Rev.
527, 529-530 (1976).
Both
the construction contract and the architect contract
designate the architect as the owner's representative
with authority to act on behalf of the owner during
the construction of the project. The architect contract
also contains a clause limiting the architect's liability
to the owner. Indeed, the contractor's performance-based
claims in the prior arbitration and in the present
action rest upon the architect's alleged faulty performance
under the architect contract. Associated Constr. Co.
v. Camp, Dresser & McKee, Inc., 646 F.Supp. 1574,
1578 (D.Conn.1986).FN3 The arbitrator recognized the
owner's liability for the architect's actions as its
project representative, and ordered the owner to pay
damages to the contractor for the architect's actions.
| |
FN3.
"If a party clearly intended to arbitrate
the transaction at issue, then that party should
not later be permitted to circumvent the prior
arbitration award by suing a person who was functionally
central to the transaction but who was technically
not a party to the arbitration." Shell, Res
Judicata and Collateral Estoppel Effects of Commercial
Arbitration, 35 UCLA L.Rev. 623, 665 (1988). |
The
contractor, however, argues that the construction
contract's "no joinder" clause, which prevented
the contractor from forcing the architect into that
arbitration, prevents the arbitrator's decision from
having any preclusive effect on the architect. We
conclude the contrary: the "no joinder"
clause underscores the privity between the architect
and the owner in the prior arbitration. As the trial
judge pointed out in his well-reasoned memorandum
of decision, "there was no reason for [the architect]
to be included in the arbitration because the [owner]
was liable for [the architect's] actions." The
first prerequisite for claim preclusion was accordingly
established by the moving party.
b.
Identity of causes of action. Claim preclusion requires
that there be an identity of causes of action in the
prior and present actions. The somewhat more narrow
doctrine of issue preclusion acts as a bar in a subsequent
action on the same or different claim only when an
issue of fact or law was actually litigated and determined
by a valid and final judgment and that determination
was essential to the judgment.
In
the prior arbitration against the owner, the contractor
claimed that the architect's acts and omissions caused
the contractor to incur additional costs for materials
and labor. The arbitrator took into account the problems
with the floor height, the structural steel, the duct
work, and the punchlist, and ordered the owner to
pay the contractor damages for additional material
and nondelay-based labor costs. In its direct action
against the architect, the contractor bases its building-related
tort claims (labeled variously, but not entirely plainly,
in the complaint as negligent misrepresentation, interference
with contractual relations, and tort) upon acts and
omissions relating to floor height, structural steel,
duct work, plaster, and punchlist problems.FN4
| |
FN4.
For example, in the current action, the contractor
claims that the architect negligently misrepresented
the elevations of certain floor heights which
resulted in a discrepancy causing substantial
damages to the contractor. The arbitrator, however,
already awarded the contractor $9,467.00 for the
"discrepancy in the plans prepared by the
Architect."
Similarly, as to the architect's acts and omissions
causing delays in the project and consequent additional
costs to the contractor, the contractor asserted
in the prior arbitration that various incidents
involving the architect delayed the project, causing
damage to the contractor. The delay claims in
the current action are based on essentially the
same facts that the contractor relied upon in
the prior arbitration, including tardy review
of submittals and structural steel drawings, failure
to grant time extensions, and issuance of an overinflated
punchlist which required substantial administrative
time to resolve. The arbitrator heard evidence
concerning, and assessed responsibility for, certain
delays as between the architect and the contractor
in connection with floor elevation plan discrepancies
and review of structural steel drawings. Such
matters were deemed arbitrable and were in fact
arbitrated. While awarding damages for additional
material and labor costs arising from the architect's
faulty performance, however, the arbitrator determined
that he had no authority to compensate the contractor
for damages specifically due to the architect's
delays. He accordingly did not award "any
additional costs associated with the employment
of a superintendent and his lost time." |
The
contractor's tort claims against the architect in
this action arising out of the architect's performance
on the project, including both building-related and
delay claims, are based on the same set of operative
facts and seek redress for the same wrongs as in the
prior arbitration. Notwithstanding the contractor's
cause of action nomenclature for its tort claims in
this litigation and its contract claims in the prior
arbitration, the causes of action in both are essentially
the same. "A claim is the same for [claim preclusion]
purposes if it is derived from the same transaction
or series of connected transactions." Saint Louis
v. Baystate Med. Center, Inc., 30 Mass.App.Ct. 393,
399, 568 N.E.2d 1181 (1991), citing Boyd v. Jamaica
Plain Co-op. Bank, 7 Mass.App.Ct. 153, 163-164, 386
N.E.2d 775 (1979). "The statement of a different
form of liability is not a different cause of action,
provided it grows out of the same transaction, act,
agreement, and seeks redress for the same wrong."
Mackintosh v. Chambers, 285 Mass. 594, 596, 190 N.E.
38 (1934). See Tuite & Sons, Inc. v. Shawmut Bank,
N.A., 43 Mass.App.Ct. 751, 753, 686 N.E.2d 1050 (1997).
Indeed, in the arbitration, the contractor contested
the very factual issues concerning responsibility,
as between itself and the architect, for actions resulting
in additional project costs which it seeks to relitigate
in this proceeding. Those factual issues were determined
by the arbitrator and were essential to the arbitration
award. See Bailey v. Metropolitan Property & Liab.
Ins. Co., 24 Mass.App.Ct. at 37, 505 N.E.2d 908. The
same facts are vital to establishing certain of the
elements of the performance-based tort claims that
the contractor now asserts in this action against
the architect.FN5 See Bradford v. Richards, 11 Mass.App.Ct.
595, 599, 417 N.E.2d 1234 (1981). We are satisfied
that the architect has shown the requisite identity
of causes of action, if not also of factual issues,
for res judicata purposes. Contrast French v. Jinright
& Ryan, P.C., Architects, 735 F.2d 433, 436 (11th
Cir.1984); Carris v. John R. Thomas & Assocs.,
896 P.2d 522, 528-529 (Okla.1995). Compare Wellons,
Inc. v. T.E. Ibberson Co., 869 F.2d 1166, 1170 (8th
Cir.1989).
| |
FN5.
By way of example, the contractor alleges that
the architect made negligent misrepresentations
in its plans regarding floor elevations. The
contractor presented evidence on the discrepancy
in plans concerning floor alignments at the
arbitration and the arbitrator found the architect
fifty percent responsible for the resulting
discrepancy in floor alignment.
c. Final judgment on the merits. Lastly, the
architect correctly maintains that the prior
arbitration constitutes a final judgment on
the merits. An arbitration award has the requisite
finality for res judicata purposes because it
can be "enforced as any other judgment
or decree." G.L. c. 251, § 14.FN6
See Restatement (Second) of Judgments §
84 (1982); Associated Constr. Co. v. Camp, Dresser
& McKee, Inc., 646 F.Supp. at 1577 ("An
arbitration award, whether or not sustained
by a court judgment constitutes finality for
res judicata"); Miles v. Aetna Cas. &
Sur. Co., 412 Mass. 424, 427, 589 N.E.2d 314
(1992). An arbitration award can have preclusive
effect if the proceeding involved the elements
of adjudicatory procedure. "When arbitration
affords opportunity for presentation of evidence
and argument substantially similar in form and
scope to judicial proceedings, the award should
have the same effect on issues necessarily determined
as a judgment has." Bailey v. Metropolitan
Property & Liab. Ins. Co., 24 Mass.App.Ct.
at 36-37, 505 N.E.2d 908, quoting from Restatement
(Second) of Judgments, § 84 comment c.
The prior arbitration occurred before an American
Arbitration Association Construction Industry
Arbitration Tribunal, in accordance with the
Commercial Arbitration Rules, which provide
for an adjudication of claims comparable to
judicial proceedings.FN7 See Bailey, supra at
n. 3.
FN6.
The contractor did not appeal the prior arbitration
pursuant to G.L. c. 251, §§ 12 &
13.
FN7.
The contractor does not dispute that the prior
arbitration would have a preclusive effect on
any subsequent suit between itself and the owner,
but contends that it should not have such effect
as to the architect, a nonparty to the arbitration,
a point we previously resolved against the contractor.
|
There
can be no serious question on this point as to the
building-related claims. The arbitrator addressed
the merits of the contractor's claims for additional
material and labor costs and set forth his reasons
for awarding or not awarding the contractor money
for specific claimed additional costs. The contractor's
effort to distinguish the delay-based claims by suggesting
that the arbitrator did not really adjudicate them
on the merits is equally unavailing.
After
the contractor concluded its proofs in the arbitration
hearing, the owner asked the arbitrator to dismiss
or strike all delay claims on the ground that they
were barred by the construction contract and G.L.
c. 30, § 39O. In response, the arbitrator issued
a detailed interim decision in which he (a) determined
that the delay claims were arbitrable under the construction
contract; (b) analyzed the evidence in light of applicable
law; and (c) concluded that he could not award the
contractor delay damages because of a "no damages
for delay" clause in the construction contract.
In the final arbitration award, the arbitrator stated
that he had no statutory authority to award damages
due to delay, and addressed the specific building-related
claims.
The
striking or dismissal of the claims seeking damages
for delay is the equivalent of a dismissal pursuant
to Mass.R.Civ.P. 12(b)(6), 365 Mass. 755 (1974), and
constitutes an adjudication on the merits for claim
preclusion purposes. Mestek, Inc. v. United Pac. Ins.
Co., 40 Mass.App.Ct. 729, 731, 667 N.E.2d 292 (1996).
Mass.R.Civ.P. 41(b)(2), 365 Mass. 804 (1974). The
arbitrator acted within his authority in determining
whether the contractor was entitled to delay damages
under the contract, and accepted evidence and argument
on the issue. This is unlike a dismissal for lack
of jurisdiction, for improper venue, or for failure
to join a party. Mass.R.Civ.P. 41(b)(3), 365 Mass.
805 (1974).FN8
| |
FN8.
Somewhat similarly, dismissal of an action on
the basis of Statute of Frauds, statute of limitations,
or the defendant's lack of capacity have been
considered sufficiently on the merits to bar a
subsequent suit under the doctrine of claim preclusion.
Smith v. Russell Sage College, 54 N.Y.2d 185,
194, 445 N.Y.S.2d 68, 429 N.E.2d 746 (1981). Velasquez
v. Franz, 123 N.J. 498, 505-513, 589 A.2d 143
(1991). See Quigley, Dismissal of Action on Statute
of Frauds and Statute of Limitations Grounds is
Sufficiently Close to Merits to Bar Subsequent
Suit Under Doctrine of Res Judicata, 56 St. John's
L.Rev. 763 (1982); Salerno, Civil Procedure-Res
Judicata, 22 Seton Hall L.Rev. 1035 (1992). |
The architect, as the moving party, accordingly demonstrated
satisfactorily the prerequisites necessary for the
application of res judicata and the trial judge correctly
determined that the contractor's tort claims arising
out of the architect's project performance were barred.
2.
Evaluation-based tort claims. The contractor alleges
that the evaluation which the architect submitted
to DCPO upon completion of the project pursuant to
G.L. c. 149, § 44D, contained intentional and
willful falsehoods, misrepresentations, and defamatory
statements about the contractor. The contractor asserts
that these statements constitute intentional and negligent
misrepresentations, fraud, deceit, and defamation.
The architect sought summary judgment as to these
claims because it asserted that proof of actual damages,
a necessary element of these evaluation-based claims,FN9
was unlikely to be forthcoming at trial. As the party
moving for summary judgment, the architect must "affirmatively
demonstrat[e] that there is no genuine issue of material
fact on every relevant issue, even if he would have
no burden on an issue if the case were to go to trial."
Pederson v. Time, Inc., 404 Mass. at 17, 532 N.E.2d
1211. The architect supported its motion by an affidavit
of its attorney and by reference to the contractor's
answers to interrogatories. We examine each in turn.
| |
FN9.
See Lakian v. Globe Newspaper Co., 399 Mass. 379,
383, 504 N.E.2d 1046 (1987) (defamation); Poly
v. Moylan, 423 Mass. 141, 149, 667 N.E.2d 250
(1996) (misrepresentation); Warner-Lambert Co.
v. Execuquest Corp., 427 Mass. 46, 47-50, 691
N.E.2d 545 (1998) (deceit). We note that the architect
did not assert the defense of qualified immunity
and we accordingly do not opine as to it. |
In
his affidavit, the architect's attorney recites that
he was informed by the contractor's attorney that
a person or persons unnamed at DCPO decided to disregard
the architect's evaluation of the contractor and accordingly
that the evaluation would not affect the contractor's
"DCPO rating." He also recited that "[a]lthough
opposing counsel has recently informed my office that
[the contractor's] DCPO rating was adversely affected
for a year and a half period, no explanation has been
given regarding how [the contractor's] rating was
directly affected by the conduct of [the architect],
or how actual damages in dollar terms were incurred."
The contractor's motion to strike this affidavit as
being in noncompliance with Mass.R.Civ.P. 56(e), 365
Mass. 825 (1974), was denied in a footnote to the
trial judge's memorandum of decision. The judge made
clear that, in his view, "it demonstrates the
lack of evidence to support [the contractor's] claim
for damages as resulting from [the architect's] submission
of the feelingmark [evaluation] to DCPO." This
was error.
Affidavits
in support of motions for summary judgment, among
other things, "shall be made on personal knowledge
[and] shall set forth such facts as would be admissible
in evidence...." Mass.R.Civ.P. 56(e). "All
affidavits or portions thereof made on information
and belief, as opposed to personal knowledge, are
to be disregarded in considering a motion for summary
judgment." Shapiro Equip. Corp. v. Morris &
Son Constr. Corp., 369 Mass. 968, 968, 341 N.E.2d
668 (1976), citing Automatic Radio Mfg. Co. v. Hazeltine
Research, Inc., 339 U.S. 827, 831, 70 S.Ct. 894, 94
L.Ed. 1312 (1950). The affidavit of the architect's
attorney was not based on his personal knowledge.
It contained blatant hearsay that would be inadmissible
at trial. See Shapiro Equip. Corp. v. Morris &
Son Constr. Corp., 369 Mass. at 968, 341 N.E.2d 668;
Pupecki v. James Madison Corp., 376 Mass. 212, 217
n. 5, 382 N.E.2d 1030 (1978). The affidavit of a party's
attorney is not exempt from the requirements of rule
56(e) and this affidavit did not comply with the rule.
Since it was duly challenged by a motion to strike,
the judge did not act within his discretion by considering
it. See Matthews v. Ocean Spray Cranberries, Inc.,
426 Mass. 122, 123 n. 1, 686 N.E.2d 1303 (1997). Compare
Madsen v. Erwin, 395 Mass. 715, 721, 481 N.E.2d 1160
(1985). The affidavit should have been struck.
In
addition to the defective affidavit, the architect
supported its motion for summary judgment by reference
to the contractor's answer to interrogatory number
twenty. In this interrogatory, the architect asked
the contractor for the basis upon which the contractor
asserted that the architect had intentionally interfered
with the contractor's relationship with DCPO. Notably,
the interrogatory asked the contractor only about
its intentional interference claim, not its other
claims arising from the evaluation. The contractor
answered that the impact of the architect's evaluation
"on TLT's future bidding capacity is significant
and ongoing." While the moving party's supporting
material need not disprove the existence of the nonmoving
party's damages, it must "demonstrate that proof
of [damages] at trial is unlikely to be forthcoming."
Kourouvacilis v. General Motors Corp., 410 Mass. 706,
714, 575 N.E.2d 734 (1991). This burden was not met
by the architect's reference to a statement by the
contractor that the complained of evaluation has a
significant and ongoing impact on its future bidding
capacity.
Because
the architect did not meet its initial burden of affirmatively
demonstrating that proof of an essential element of
the evaluation-based claims, damages, was unlikely
to be forthcoming, summary judgment for the architect
on such claims should not have entered. See Smith
v. Massimiano, 414 Mass. 81, 86-87, 605 N.E.2d 292
(1993).
3.
G. L. c. 93A claims. The contractor claims that the
architect engaged in unfair and deceptive trade practices
in violation of G.L. c. 93A. It bases these allegations
on conduct giving rise to its other claims, namely
the architect's project performance and its submission
of the evaluation to DCPO. The trial judge granted
the architect's motion for summary judgment on all
claims without specific explanation of his treatment
of the G.L. c. 93A claims. Nonetheless, we think the
judge likely disposed of the G.L. c. 93A claims which
arose from the architect's performance on the basis
of res judicata, and the G.L. c. 93A claims which
arose from the evaluation to DCPO on the basis of
lack of damages. We discuss these in reverse order.
The
architect contends that actual damages is a necessary
element of a G.L. c. 93A, § 11, claim and, since
the contractor would be unable to prove damages for
the evaluation-based torts, it would also be unable
to prove damages for its evaluation-based G.L. c.
93A claim. For the reasons just discussed, summary
judgment on the contractor's evaluation-based claims
because of lack of proof of damages was improvidently
granted. Hence, the contractor's G.L. c. 93A claims
based on the evaluation also survive. See Dulgarian
v. Stone, 420 Mass. 843, 853, 652 N.E.2d 603 (1995).
("Defamatory statements are actionable under
G.L. c. 93A [, § 11].... However, where allegedly
defamatory statements do not support a cause of action
for defamation, they also do not support a cause of
action under G.L. c. 93A [, § 11]").
Turning
now to the performance-based G.L. c. 93A claims, we
must determine whether, they, like the performance-based
tort claims, are barred by res judicata. There is
nothing in the record before us to suggest that the
parties intended to litigate the c. 93A claims in
the arbitration proceedings, or that the arbitrator
was asked to consider or decide such claims.FN10 Accordingly,
in the circumstances of this case, the architect,
as the moving party, did not meet its burden of showing
that such claims are barred by res judicata and it
was error to dismiss the contractor's G.L. c. 93A
performance-based claims on this basis. See Louison
v. Fischman, 341 Mass. 309, 313, 168 N.E.2d 340 (1960);
Bailey v. Metropolitan Property & Liab. Ins. Co.,
24 Mass.App.Ct. at 36-37, 505 N.E.2d 908.
| |
FN10.
Massachusetts courts have not yet determined whether
and when municipalities are amenable to suit under
G.L. c. 93A, § 11, see U.S. Leasing Corp.
v. City of Chicopee, 402 Mass. 228, 232, 521 N.E.2d
741 (1988); All Seasons Servs., Inc. v. Commissioner
of Health & Hosps. of Boston, 416 Mass. 269,
271, 620 N.E.2d 778 (1993), and we do not decide
this now. |
Conclusion.
We affirm the portion of the judgment dismissing the
contractor's tort claims based on the architect's
performance during the project, reverse the portion
of the judgment dismissing the contractor's tort claims
based on the evaluation, reverse the portion of the
judgment dismissing the contractor's G.L. c. 93A,
§ 11, claims, and remand the case to the Superior
Court for further proceedings.
So
ordered.
back to top
|